Location: Maroochydore, Queensland
Client: NPE / Vantage Building Group
Duration: November 2019 – Current
Project Overview:
Clearpro was engaged as the water treatment contractor on a 12-storey high-rise development. Dewatering for the two-storey basement was carried out by National Pump and Energy with Clearpro providing water treatment and environmental monitoring services. Clearpro’s water treatment system consists of one LB15 water treatment system and two additional clarifying tanks designed to maintain effective treatment at up to 10L/s. Removal of dissolved iron and pH correction is required to effectively treat groundwater to a high standard prior to release into the nearby Maroochy River. Weekly sampling and field monitoring was carried out to ensure the quality of the discharge and receiving waterway.