Location: Currumbin Creek, QLD
Client: SEE Civil PTY LTD / TMR
Duration: May 2024 – December 2024
Project Overview:
The slope remediation works, and embankment repairs were undertaken in 2 locations along Currumbin Creek Road as part of a project to construct stable and secure bank foundations in areas of high susceptibility to bank scouring.
Clearpro played an important role in maintaining a dry work area within the sheet pile cofferdam effectively removing and treating all construction contaminated water. A multi-faceted dewatering approach was needed to separate clean creek water from the highly disturbed sediment laden. By customising a water treatment system specifically for the application, we were able to ensure that the challenging project was able to proceed without any delays due to either non-compliant water or a flooded work zone.